Project 35: Classic Center Energy Management

Description


This project installed a control system for the mechanical systems, allowing the ability to better manage energy. Improvements included replacing existing dividing walls in the ballroom with higher rated acoustical walls and purchasing lighting instruments for the theater.

Budget


  • Original SPLOST Budget: $691,900
  • Budget Amendments: -$26,586
  • Adjusted SPLOST Budget: $665,314
  • Amount Expended: $665,314

Was this page helpful for you? Yes No