Project 22: Classic Center Theatre Package

Project Description


This project included the replacement and repair of the existing sprinkler system within the theater, renovations to the theater heating system, repainting and carpet replacement in various areas, relocation of the sound booth, improvements to the lighting system, improvements to stage access for more efficient movement of equipment, replacement of the orchestra shell, installation of fixed beverage and concession stations, and improvements to dressing rooms and theater office space.

Project Details


  • Project Sponsor: Classic Center
  • Type: Facilities
  • Project Manager: Don Martin

Status: August 31, 2012


  • All components of the project were completed in 2006.
  • Expended: $1,788,466

Budget

Fiscal Period
Amount
FY 2006 (Tier 1) $1,688,207
FY 2007 (Tier 2) $105,700
Total for this project:
$1,793,907